4. Project Phases (Sequential Workflow)
|
||||
|
||||
This project will be developed using a sequential workflow, focusing on completing the backend API before starting on the frontend implementation.
|
||||
Phase 1: Foundation & API Design (Week 1)
|
||||
|
||||
Focus: Setting up project structures and defining the API contract.
|
||||
|
||||
Tasks:
|
||||
|
||||
Initialize the Next.js and Go (Echo) projects in separate GitHub repositories.
|
||||
|
||||
Design the complete GraphQL schema. This schema is the definitive contract between the frontend and backend.
|
||||
|
||||
Design the modular Go interface for backend integrations.
|
||||
|
||||
Establish the PostgreSQL database connection in the Go project.
|
||||
|
||||
Set up the basic Next.js project with a GraphQL client.
|
||||
|
||||
Phase 2: Core Backend Development (Weeks 2-5)
|
||||
|
||||
Focus: Building a complete and stable backend API. The frontend project is paused.
|
||||
|
||||
Tasks:
|
||||
|
||||
Implement the full PostgreSQL database schema.
|
||||
|
||||
Build the user authentication system using JWTs.
|
||||
|
||||
Write all GraphQL resolvers for the core features (users, projects, etc.).
|
||||
|
||||
Implement the backend logic for the integration system.
|
||||
|
||||
Build a proof-of-concept integration package (e.g., for GitHub).
|
||||
|
||||
Write comprehensive unit and integration tests for the API.
|
||||
|
||||
Phase 3: Frontend Development & Connection (Weeks 6-8)
|
||||
|
||||
Focus: Building the user interface and connecting it to the now-stable backend API.
|
||||
|
||||
Tasks:
|
||||
|
||||
Connect the Next.js GraphQL client to the live Go backend endpoint.
|
||||
|
||||
Build all UI components and pages (login, dashboard, project views).
|
||||
|
||||
Implement the full client-side authentication flow (sending credentials, storing JWTs).
|
||||
|
||||
Write all necessary GraphQL queries and mutations to interact with the API.
|
||||
|
||||
Perform end-to-end testing of all user flows.
|
||||
|
||||
Phase 4: Final Testing & Deployment (Week 9)
|
||||
|
||||
Focus: Preparing for launch and deploying both services.
|
||||
|
||||
Tasks:
|
||||
|
||||
Dockerize the Go application.
|
||||
|
||||
Set up a CI/CD pipeline and deploy the backend container to a cloud provider.
|
||||
|
||||
Configure the Next.js application for production and deploy it to Vercel.
|
||||
|
||||
Perform final integration and smoke testing on the live environment.
|
||||
|
||||
Phase 5: Post-Launch & Maintenance (Ongoing)
|
||||
|
||||
Focus: Monitoring, iterating, and improving the live application.
|
||||
|
||||
Tasks:
|
||||
|
||||
Monitor the performance and logs of both services.
|
||||
|
||||
Gather user feedback for future improvements.
|
||||
|
||||
Plan and develop new backend integrations and frontend features.
|
||||